3Projects in the shown registers
1,200 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Built: 1.2 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 1.2 |
| Queued | 0.0 |
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 3 | 1,200 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Hornsea Power Station 1B | Offshore wind | 400 MW | not stated | Built | Hornsea Platform 1B Offshore Substation |
| Hornsea Power Station 1C | Offshore wind | 400 MW | not stated | Built | Hornsea Platform 1C Offshore Substation |
| Hornsea Power Station 1A | Offshore wind | 400 MW | not stated | Built | Hornsea Platform 1A Offshore Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data