99.9 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 0.1 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued0.1
MW by technology
TechnologyProjectsMW
Battery storage199.9 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Forsa Energy Denny BESSBattery storage99.9 MW31 Oct 2030ScopingFORSA ENERGY DENNY BESS 132KV GRID SUPPLY POINT SUBSTATION

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.