Danks Way BESS

Developer as published, connection site, reference: OCKER HILL BESS LIMITED. Ocker Hill C 132kV GSP (NGET). PRO-006863.

Sign in to watch this project
Capacity99.4 MWBattery storage
Connection date31 Oct 2026Status as printed: Under Construction/Commissioning
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20262027File dated 2026-09-08: connection date 2026-10-31Oct 2026File dated 2026-10-20: connection date 2026-10-318 Sep202620 Oct2026
20262027File dated 2026-09-08: connection date 2026-10-31Oct 2026File dated 2026-10-20: connection date 2026-10-318 Sep202620 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 8 Sep 2026 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data