N84 Grid

Tarchon

Developer as published, connection site, reference: Tarchon Energy Limited. East Anglia Connection Node 400kV Substation (NGET). PRO-001289.

Sign in to watch this project
Capacity1,400 MWInterconnector
Connection date31 Oct 2030Status as printed: Scoping
First date seen 31 Oct 2026, difference +1461 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20302031File dated 2022-02-15: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2030-10-3115 Feb202220 Oct2026
20302031File dated 2022-02-15: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2030-10-3115 Feb202220 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 15 Feb 2022 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.