Capacity200 MWHybrid, Gate 1
Connection date4 Apr 2033Status as printed: Scoping
MW ahead in N84's order at this site0 MWcalculated by N84
Connection date, edition by edition
The connection date is printed the same in every file N84 holds for this project, from 27 Sep 2024 to 20 Oct 2026. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
No changes observed in the files N84 holds for this window.
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.