Solomons Farm BESS

Developer as published, connection site, reference: Solomons BESS Ltd. North Kent Connection Node B 132kV Substation (NGET). PRO-003181.

Sign in to watch this project
Capacity240 MWBattery storage, Gate 1
Connection date31 Oct 2033Status as printed: Scoping
First date seen 31 Oct 2030, difference +1096 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20302031203220332034File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2033-10-31Oct 203311 Sep202620 Oct2026
20302031203220332034File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2033-10-31Oct 203311 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1868Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1841
  2. 20 Oct 2026. MW Effective From printed as 31 Oct 2033 (previous file: 31 Oct 2030), 1,096 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1096 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1868Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1841

Supported by National Energy SO Open Data