Developer as published, connection site, reference: Don Cossack Ltd. Tynemouth 275kV Substation (NGET). PRO-003875.

Sign in to watch this project
Capacity70 MWBattery storage
Connection date15 Jun 2034Status as printed: Awaiting Consents
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20342035File dated 2024-05-31: connection date 2034-06-15Jun 2034File dated 2026-10-20: connection date 2034-06-1531 May202420 Oct2026
20342035File dated 2024-05-31: connection date 2034-06-15Jun 2034File dated 2026-10-20: connection date 2034-06-1531 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Awaiting Consents (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Awaiting ConsentsReceipt: NESO TEC Register, file dated 20 Oct 2026, row 606Receipt: NESO TEC Register, file dated 11 Sep 2026, row 597

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.