Developer as published, connection site, reference: SCOTTISHPOWER RENEWABLES (UK) LIMITED. Hollandmey Renewable Energy Development132/33kV Substation (SHET). PRO-001094.

Sign in to watch this project
Capacity49.5 MWOnshore wind
Connection date31 May 2030Status as printed: Consents Approved
First date seen 1 May 2029, difference +395 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20302031File dated 2024-05-31: connection date 2030-05-31May 2030File dated 2026-10-20: connection date 2030-05-3131 May202420 Oct2026
20302031File dated 2024-05-31: connection date 2030-05-31May 2030File dated 2026-10-20: connection date 2030-05-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.