Frome Valley Energy Park

Developer as published, connection site, reference: BIOSOUTH ENERGY LIMITED. Chickerell-Mannington 400kV Substation (NGET). PRO-006617.

Sign in to watch this project
Capacity43.2 MWHybrid, Gate 1
Connection date31 Oct 2039Status as printed: Scoping
First date seen 31 Oct 2037, difference +730 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

2037203820392040File dated 2026-09-11: connection date 2037-10-31Oct 2037File dated 2026-10-20: connection date 2039-10-31Oct 203911 Sep202620 Oct2026
2037203820392040File dated 2026-09-11: connection date 2037-10-31Oct 2037File dated 2026-10-20: connection date 2039-10-31Oct 203911 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2039 (previous file: 31 Oct 2037), 730 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +730 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 835Receipt: NESO TEC Register, file dated 11 Sep 2026, row 814