N84 Grid

Braegrundie Farm (AEUK BATTERY PROJECT III LTD)

Developer as published, connection site, reference: AEUK BATTERY PROJECT III LTD. Braegrundie Farm 132kV Substation (SHET). PRO-004674.

Sign in to watch this project
Capacity95 MWBattery storage, Gate 1
Connection date30 Jun 2030Status as printed: Awaiting Consents
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20302031File dated 2024-05-31: connection date 2030-06-30Jun 2030File dated 2026-10-20: connection date 2030-06-3031 May202420 Oct2026
20302031File dated 2024-05-31: connection date 2030-06-30Jun 2030File dated 2026-10-20: connection date 2030-06-3031 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.