N84 Grid

Rye House (Tertiary)

Developer as published, connection site, reference: ENSO GREEN HOLDINGS N LIMITED. Rye House 400kV Substation (NGET). PRO-000564. Removed from the register (not present in two consecutive files)

Sign in to watch this project
Capacity0 MWBattery storage
Connection date31 Oct 2027Status as printed: Scoping
First date seen 31 Oct 2025, difference +730 dayscalculated by N84
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20272028File dated 2024-05-31: connection date 2027-10-31Oct 2027File dated 2025-03-21: connection date 2027-10-3131 May202421 Mar2025
20272028File dated 2024-05-31: connection date 2027-10-31Oct 2027File dated 2025-03-21: connection date 2027-10-3131 May202421 Mar2025

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 21 Mar 2025. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.