N84 Grid

Bramford GEC (Ethos Green)

Developer as published, connection site, reference: BRAMFORD GREEN ENERGY CENTRE LTD. Bramford B 400kV Substation (NGET). PRO-004027.

Sign in to watch this project
Capacity650 MWHybrid, Gate 1
Connection date1 Jun 2032Status as printed: Awaiting Consents
First date seen 30 Oct 2033, difference -516 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

203220332034File dated 2026-09-11: connection date 2033-10-30Oct 2033File dated 2026-10-20: connection date 2032-06-01Jun 203211 Sep202620 Oct2026
203220332034File dated 2026-09-11: connection date 2033-10-30Oct 2033File dated 2026-10-20: connection date 2032-06-01Jun 203211 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 1 Jun 2032 (previous file: 30 Oct 2033), 516 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -516 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 259Receipt: NESO TEC Register, file dated 11 Sep 2026, row 256

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.