N84 Grid

MILFORD (solar)

Developer as published, connection site, reference: MILFORD. SSEN-50KW-4d28bafbf68b. Removed from the register (not present in two consecutive files)

Sign in to watch this project
Capacity0 MWSolar
Connection date31 Dec 2025Status as printed: Accepted to Connect
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20252026File dated 2025-09-01: connection date 2025-12-31Dec 2025File dated 2025-11-01: connection date 2025-12-311 Sep20251 Nov2025
20252026File dated 2025-09-01: connection date 2025-12-31Dec 2025File dated 2025-11-01: connection date 2025-12-311 Sep20251 Nov2025

The connection date is printed the same in every file N84 holds for this project, from 1 Sep 2025 to 1 Nov 2025. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.