Whitehouse BESS station

Developer as published, connection site, reference: IGP INTERNATIONAL PROSPECTING LIMITED. Whitehouse 275kV Substation (SHET). PRO-002237.

Sign in to watch this project
Capacity249 MWBattery storage, Gate 1
Connection date31 Oct 2034Status as printed: Scoping
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

2032203320342035File dated 2026-09-11: connection date 2032-07-31Jul 2032File dated 2026-10-20: connection date 2034-10-31Oct 203411 Sep202620 Oct2026
2032203320342035File dated 2026-09-11: connection date 2032-07-31Jul 2032File dated 2026-10-20: connection date 2034-10-31Oct 203411 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 2147Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2118
  2. 20 Oct 2026. MW Effective From printed as 31 Oct 2034 (previous file: 31 Jul 2032), 822 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +822 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2147Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2118

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.