Stella Battery Energy Storage

Developer as published, connection site, reference: CAPELLA BESS LTD. Stella South GSP (NGET). PRO-005112.

Sign in to watch this project
Capacity78 MWBattery storage, Gate 2
Connection date30 Nov 2026Status as printed: Consents Approved
First date seen 27 Sep 2025, difference +429 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

202520262027File dated 2026-09-11: connection date 2025-09-27Sep 2025File dated 2026-10-20: connection date 2026-11-30Nov 202611 Sep202620 Oct2026
202520262027File dated 2026-09-11: connection date 2025-09-27Sep 2025File dated 2026-10-20: connection date 2026-11-30Nov 202611 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1922Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1895
  2. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1922Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1895
  3. 20 Oct 2026. MW Effective From printed as 30 Nov 2026 (previous file: 27 Sep 2025), 429 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +429 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1922Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1895

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.