Capacity100 MWOffshore wind, Gate 2
Connection date3 Apr 2028Status as printed: Consents Approved
First date seen 31 Aug 2025, difference +946 dayscalculated by N84
First date seen 31 Aug 2025, difference +946 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1667Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1641
- 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1667Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1641
- 20 Oct 2026. MW Effective From printed as 3 Apr 2028 (previous file: 31 Oct 2027), 155 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +155 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1667Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1641
Supported by National Energy SO Open Data