N84 Grid

Wymondham Road Farm

Developer as published, connection site, reference: QAIR RENEWABLES UK LIMITED. North Anglia Connection Node A 400kV (NGET). PRO-004441.

Sign in to watch this project
Capacity228 MWBattery storage, Gate 1
Connection date31 Oct 2034Status as printed: Scoping
MW ahead in N84's order at this site1,829.9 MWcalculated by N84

Connection date, edition by edition

20342035File dated 2025-03-21: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3121 Mar202520 Oct2026
20342035File dated 2025-03-21: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3121 Mar202520 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 21 Mar 2025 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.