N84 Grid

Craighead Wind Farm (GALILEO 02 LIMITED)

Developer as published, connection site, reference: GALILEO 02 LIMITED. CRAIGHEAD WIND FARM 132kV SUBSTATION (SPT). PRO-002821.

Sign in to watch this project
Capacity77 MWOnshore wind, Gate 1
Connection date29 Oct 2032Status as printed: Scoping
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20322033File dated 2025-07-22: connection date 2032-10-29Oct 2032File dated 2026-10-20: connection date 2032-10-2922 Jul202520 Oct2026
20322033File dated 2025-07-22: connection date 2032-10-29Oct 2032File dated 2026-10-20: connection date 2032-10-2922 Jul202520 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 22 Jul 2025 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 507Receipt: NESO TEC Register, file dated 11 Sep 2026, row 498

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.