Market Harborough

Developer as published, connection site, reference: CONNECTID 1 LIMITED. West Anglia Connection Node F 400kV Substation (NGET). PRO-003271.

Sign in to watch this project
Capacity700 MWHybrid
Connection date31 Oct 2034Status as printed: Awaiting Consents
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20342035File dated 2024-05-31: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3131 May202420 Oct2026
20342035File dated 2024-05-31: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Awaiting Consents (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Awaiting ConsentsReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1376Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1356