Capacity170 MWBattery storage, Gate 1
Connection date31 Jul 2030Status as printed: Scoping
First date seen 1 Oct 2029, difference +303 dayscalculated by N84
First date seen 1 Oct 2029, difference +303 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. MW Effective From printed as 31 Jul 2030 (previous file: 1 Oct 2029), 303 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +303 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 715Receipt: NESO TEC Register, file dated 11 Sep 2026, row 696
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.