Limekiln

Developer as published, connection site, reference: Limekiln Extension Limited. Limekilns 132/33kV substation (SHET). PRO-000515.

Sign in to watch this project
Capacity167 MWHybrid, Gate 1
Connection date1 Dec 2030Status as printed: Scoping
First date seen 30 Apr 2024, difference +2406 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20302031File dated 2024-05-31: connection date 2030-12-01Dec 2030File dated 2025-07-22: connection date 2030-12-0131 May202422 Jul2025
20302031File dated 2024-05-31: connection date 2030-12-01Dec 2030File dated 2025-07-22: connection date 2030-12-0131 May202422 Jul2025

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 22 Jul 2025. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Scoping (previous file: Consents Approved). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedConsents Approved → ScopingReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1289Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1269
  2. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1289Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1269

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.