Wymondley GEC (Ethos Green)

Developer as published, connection site, reference: WYMONDLEY GREEN ENERGY CENTRE LTD. Wymondley 2 400kV Substation (NGET). PRO-003934.

Sign in to watch this project
Capacity700 MWHybrid, Gate 1
Connection date30 Oct 2032Status as printed: Awaiting Consents
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20322033File dated 2024-05-31: connection date 2032-10-30Oct 2032File dated 2026-10-20: connection date 2032-10-3031 May202420 Oct2026
20322033File dated 2024-05-31: connection date 2032-10-30Oct 2032File dated 2026-10-20: connection date 2032-10-3031 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 2204Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2176