N84 Grid

MINTLAW (solar)

Developer as published, connection site, reference: MINTLAW. SSEN-50KW-e8d2d628fb0b. Removed from the register (not present in two consecutive files)

Sign in to watch this project
Capacity0 MWSolar
Connection date9 Jan 2027Status as printed: Accepted to Connect
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20272028File dated 2026-03-01: connection date 2027-01-09Jan 2027File dated 2026-05-01: connection date 2027-01-091 Mar20261 May2026
20272028File dated 2026-03-01: connection date 2027-01-09Jan 2027File dated 2026-05-01: connection date 2027-01-091 Mar20261 May2026

The connection date is printed the same in every file N84 holds for this project, from 1 Mar 2026 to 1 May 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.