N84 Grid

Upper Beoch Windfarm

Developer as published, connection site, reference: BROCKWELL ENERGY LIMITED. New Cumnock North 132kV Substation (SPT). PRO-004068.

Sign in to watch this project
Capacity80 MWOnshore wind, Gate 1
Connection date31 Jul 2036Status as printed: Scoping
First date seen 31 Oct 2033, difference +1004 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20332034203520362037File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2036-07-31Jul 203611 Sep202620 Oct2026
20332034203520362037File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2036-07-31Jul 203611 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Jul 2036 (previous file: 31 Oct 2033), 1,004 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1004 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2063Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2035

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.