North Kyle New Cumnock

Developer as published, connection site, reference: NORTH KYLE WIND FARM LIMITED. North Kyle 132/33kV substation (SPT). PRO-000474.

Sign in to watch this project
Capacity212 MWOnshore wind, Gate 2
Connection datenot statedStatus as printed: Built
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

No date history to draw

The files N84 holds in your history window print no connection date for this project.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Not printed in two consecutive files. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedmissing → left_registerReceipt: NESO TEC Register, file dated 20 Oct 2026Receipt: NESO TEC Register, file dated 8 Sep 2026, row 1541
  2. 20 Oct 2026. Not printed in two consecutive files. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedmissing → left_registerReceipt: NESO TEC Register, file dated 20 Oct 2026Receipt: NESO TEC Register, file dated 8 Sep 2026, row 1540

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.