N84 Grid

TAIN (hybrid)

Developer as published, connection site, reference: TAIN. SSEN-50KW-29116674adb3. Removed from the register (not present in two consecutive files)

Sign in to watch this project
Capacity0 MWHybrid
Connection date31 Aug 2026Status as printed: Accepted to Connect
First date seen 17 Feb 2027, difference -170 dayscalculated by N84
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20262027File dated 2026-03-01: connection date 2026-08-31Aug 2026File dated 2026-05-01: connection date 2026-08-311 Mar20261 May2026
20262027File dated 2026-03-01: connection date 2026-08-31Aug 2026File dated 2026-05-01: connection date 2026-08-311 Mar20261 May2026

The connection date is printed the same in every file N84 holds for this project, from 1 Mar 2026 to 1 May 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.