N84 Grid

Abernethy GSP

NESO connection site, host SHET.

Contracted here0.18 GWNot yet connected, as printed
Entries in the queue10entries with a printed MW
Earliest connection date31 Aug 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue70.18 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Abernethy GSP (DNO) (Industrial Estate Friarton Road)7 Nov 202531 Aug 20230.14 MW
Glendoick Garden Centre7 Nov 202517 Jan 20240.15 MW
Cordon Farm PV7 Nov 202531 May 20249.9 MW
Carey Farm PV7 Nov 202531 May 20249.9 MW
Water Treatment Works - Glendevon7 Nov 202530 Sep 20240.19 MW
PM AB Energy Storage7 Nov 202531 Oct 202649.9 MW
PM AB2 Energy Storage7 Nov 202531 Oct 202815 MW
Binn Ecopark7 Nov 202531 Oct 20289.9 MW
Balgonie Farm7 Nov 202531 Oct 202850 MW
Cordon Farm BESS7 Nov 202531 Oct 203330 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2023: 0 MW2024: 20 MW2026: 70 MW2028: 145 MW2033: 175 MW202320252027202920312033175 MW
0 MW100 MW200 MW2023: 0 MW2024: 20 MW2026: 70 MW2028: 145 MW2033: 175 MW2023202620292033175 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20230.14 MW
202420.28 MW
202670.18 MW
2028145.08 MW
2033175.08 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Abernethy GSP (DNO) (Industrial Estate Friarton Road)0.14 MW0 MW31 Aug 2023not statedgate not printedScoping
2Glendoick Garden Centre0.15 MW0.14 MW17 Jan 2024not statedgate not printedScoping
3Cordon Farm PV9.9 MW0.29 MW31 May 2024not statedgate not printedConsents Approved
4Carey Farm PV9.9 MW10.19 MW31 May 2024not statedgate not printedConsents Approved
5Water Treatment Works - Glendevon0.19 MW20.09 MW30 Sep 2024not statedgate not printedScoping
6PM AB Energy Storage49.9 MW20.28 MW31 Oct 2026not statedgate not printedScoping
7PM AB2 Energy Storage15 MW70.18 MW31 Oct 2028not statedgate not printedScoping
8Binn Ecopark9.9 MW85.18 MW31 Oct 2028not statedgate not printedScoping
9Balgonie Farm50 MW95.08 MW31 Oct 20281gate 1Scoping
10Cordon Farm BESS30 MW145.08 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202310.14 MW
2024420.14 MW
2026149.9 MW
2028374.9 MW
2033130 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Balgonie FarmBattery storage50 MW31 Oct 2028Scoping
PM AB Energy StorageBattery storage49.9 MW31 Oct 2026Scoping
Cordon Farm BESSBattery storage30 MW31 Oct 2033Scoping
Jamesfield Farm Battery StorageBattery storage30 MWnot statedBuilt
Jamesfield Farm Phase 2 Battery StorageBattery storage19 MWnot statedBuilt
PM AB2 Energy StorageBattery storage15 MW31 Oct 2028Scoping
Binn EcoparkBiomass and waste9.9 MW31 Oct 2028Scoping
Carey Farm PVSolar9.9 MW31 May 2024Consents Approved
Cordon Farm PVSolar9.9 MW31 May 2024Consents Approved
Errol PV Generating StationSolar9.9 MWnot statedBuilt
Binn Wind Generating StationOnshore wind9.4 MWnot statedBuilt
Water Treatment Works - GlendevonHybrid0.19 MW30 Sep 2024Scoping
Glendoick Garden CentreSolar0.15 MW17 Jan 2024Scoping
Abernethy GSP (DNO) (Industrial Estate Friarton Road)Solar0.14 MW31 Aug 2023Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.