ABERNETHY 2 400/33KV GRID SUPPLY POINT SUBSTATION

NESO connection site, host SHET.

Contracted here0.28 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue279.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Shire End Solar Farm22 Jul 202531 Oct 203320 MW
Balgonie Farm BESS7 Nov 202531 Oct 203349.9 MW
Balgonie Solar and BESS7 Nov 202531 Oct 203360 MW
Jamesfield Farm7 Nov 202531 Oct 203360 MW
Fragland Solar and BESS7 Nov 202531 Oct 203360 MW
Binn Solar Farm7 Nov 202531 Oct 203530 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2033: 250 MW2035: 280 MW203320342035280 MW
0 MW200 MW400 MW2033: 250 MW2035: 280 MW203320342035280 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033249.9 MW
2035279.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Shire End Solar Farm20 MW0 MW31 Oct 2033not statedgate not printedScoping
2Balgonie Farm BESS49.9 MW20 MW31 Oct 20331gate 1Scoping
3Balgonie Solar and BESS60 MW69.9 MW31 Oct 20331gate 1Scoping
4Jamesfield Farm60 MW129.9 MW31 Oct 20331gate 1Scoping
5Fragland Solar and BESS60 MW189.9 MW31 Oct 20331gate 1Scoping
6Binn Solar Farm30 MW249.9 MW31 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20335249.9 MW
2035130 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Jamesfield FarmHybrid60 MW31 Oct 2033Scoping
Fragland Solar and BESSHybrid60 MW31 Oct 2033Scoping
Balgonie Solar and BESSHybrid60 MW31 Oct 2033Scoping
Balgonie Farm BESSBattery storage49.9 MW31 Oct 2033Scoping
Binn Solar FarmHybrid30 MW31 Oct 2035Scoping
Shire End Solar FarmSolar20 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data