The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Aberthaw Energy
31 May 2024 to 30 Oct 2028 (gate 1) - Aberthaw (Tertiary)
31 May 2024 to 31 Oct 2029 (gate 1) - Afon Ddaw
31 May 2024 to 31 Oct 2029 (gate not printed) - Aberthaw PV & BESS Generation
31 May 2024 to 31 Oct 2029 (gate 1) - Mwyndy Storage
22 Jul 2025 to 30 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Aberthaw Energy | 31 May 2024 | 30 Oct 2028 | 249 MW |
| Aberthaw (Tertiary) | 31 May 2024 | 31 Oct 2029 | 57 MW |
| Afon Ddaw | 31 May 2024 | 31 Oct 2029 | 249 MW |
| Aberthaw PV & BESS Generation | 31 May 2024 | 31 Oct 2029 | 200 MW |
| Mwyndy Storage | 22 Jul 2025 | 30 Oct 2037 | 249 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2028 | 249 MW |
| 2029 | 755 MW |
| 2037 | 1,004 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Aberthaw Energy | 249 MW | 0 MW | 30 Oct 2028 | 1 | gate 1 | Scoping |
| 2 | Aberthaw (Tertiary) | 57 MW | 249 MW | 31 Oct 2029 | 1 | gate 1 | Scoping |
| 3 | Afon Ddaw | 249 MW | 306 MW | 31 Oct 2029 | not stated | gate not printed | Scoping |
| 4 | Aberthaw PV & BESS Generation | 200 MW | 555 MW | 31 Oct 2029 | 1 | gate 1 | Scoping |
| 5 | Mwyndy Storage | 249 MW | 755 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2028 | 1 | 249 MW |
| 2029 | 3 | 506 MW |
| 2037 | 1 | 249 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Mwyndy Storage | Battery storage | 249 MW | 30 Oct 2037 | Scoping |
| Aberthaw Energy | Battery storage | 249 MW | 30 Oct 2028 | Scoping |
| Afon Ddaw | Hybrid | 249 MW | 31 Oct 2029 | Scoping |
| Aberthaw PV & BESS Generation | Battery storage | 200 MW | 31 Oct 2029 | Scoping |
| Aberthaw (Tertiary) | Hybrid | 57 MW | 31 Oct 2029 | Scoping |
| Peak Gen Barry | Battery storage | 20 MW | not stated | Built |