N84 Grid

Aberthaw 275kV Substation

NESO connection site, host NGET.

Contracted here1.00 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date30 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,004 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Aberthaw Energy31 May 202430 Oct 2028249 MW
Aberthaw (Tertiary)31 May 202431 Oct 202957 MW
Afon Ddaw31 May 202431 Oct 2029249 MW
Aberthaw PV & BESS Generation31 May 202431 Oct 2029200 MW
Mwyndy Storage22 Jul 202530 Oct 2037249 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 249 MW2029: 755 MW2037: 1.0 GW2028203020322034203620371.0 GW
0 MW1.0 GW2.0 GW2028: 249 MW2029: 755 MW2037: 1.0 GW20282031203420371.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028249 MW
2029755 MW
20371,004 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Aberthaw Energy249 MW0 MW30 Oct 20281gate 1Scoping
2Aberthaw (Tertiary)57 MW249 MW31 Oct 20291gate 1Scoping
3Afon Ddaw249 MW306 MW31 Oct 2029not statedgate not printedScoping
4Aberthaw PV & BESS Generation200 MW555 MW31 Oct 20291gate 1Scoping
5Mwyndy Storage249 MW755 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281249 MW
20293506 MW
20371249 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mwyndy StorageBattery storage249 MW30 Oct 2037Scoping
Aberthaw EnergyBattery storage249 MW30 Oct 2028Scoping
Afon DdawHybrid249 MW31 Oct 2029Scoping
Aberthaw PV & BESS GenerationBattery storage200 MW31 Oct 2029Scoping
Aberthaw (Tertiary)Hybrid57 MW31 Oct 2029Scoping
Peak Gen BarryBattery storage20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.