AGS CALDERSIDE 275KV SUBSTATION

NESO connection site, host SPT.

Contracted here0.50 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue500 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
AGS Calderside Battery Energy Storage System31 May 202431 Oct 2029300 MW
AGS Calderside Battery Energy Storage System31 May 202431 Oct 2033200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2029: 300 MW2033: 500 MW20292030203120322033500 MW
0 MW250 MW500 MW2029: 300 MW2033: 500 MW202920312033500 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029300 MW
2033500 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1AGS Calderside Battery Energy Storage System300 MW0 MW31 Oct 20291gate 1Scoping
2AGS Calderside Battery Energy Storage System200 MW300 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291300 MW
20331200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
AGS Calderside Battery Energy Storage SystemBattery storage500 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data