The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Knockton Wind Farm
31 May 2024 to 31 Oct 2033 (gate not printed) - ALYTH ENERGY STORAGE AND SOLAR
22 Jul 2025 to 31 Oct 2033 (gate 1) - Brigton of Ruthven BESS
22 Jul 2025 to 31 Oct 2033 (gate not printed) - Glenmoy Wind Solar & BESS
27 Mar 2026 to 31 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Knockton Wind Farm | 31 May 2024 | 31 Oct 2033 | 130.2 MW |
| ALYTH ENERGY STORAGE AND SOLAR | 22 Jul 2025 | 31 Oct 2033 | 400 MW |
| Brigton of Ruthven BESS | 22 Jul 2025 | 31 Oct 2033 | 500 MW |
| Glenmoy Wind Solar & BESS | 27 Mar 2026 | 31 Oct 2037 | 224 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2033 | 1,030.2 MW |
| 2037 | 1,254.2 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Knockton Wind Farm | 130.2 MW | 0 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 2 | ALYTH ENERGY STORAGE AND SOLAR | 400 MW | 130.2 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 3 | Brigton of Ruthven BESS | 500 MW | 530.2 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 4 | Glenmoy Wind Solar & BESS | 224 MW | 1,030.2 MW | 31 Oct 2037 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2033 | 3 | 1,030.2 MW |
| 2037 | 1 | 224 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Brigton of Ruthven BESS | Battery storage | 500 MW | 31 Oct 2033 | Scoping |
| ALYTH ENERGY STORAGE AND SOLAR | Hybrid | 400 MW | 31 Oct 2033 | Scoping |
| Glenmoy Wind Solar & BESS | Hybrid | 224 MW | 31 Oct 2037 | Scoping |
| Knockton Wind Farm | Onshore wind | 130.2 MW | 31 Oct 2033 | Scoping |