N84 Grid

Alyth 400kV Substation

NESO connection site, host SHET.

Contracted here1.25 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,254.2 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Knockton Wind Farm31 May 202431 Oct 2033130.2 MW
ALYTH ENERGY STORAGE AND SOLAR22 Jul 202531 Oct 2033400 MW
Brigton of Ruthven BESS22 Jul 202531 Oct 2033500 MW
Glenmoy Wind Solar & BESS27 Mar 202631 Oct 2037224 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2033: 1.0 GW2037: 1.3 GW203320342035203620371.3 GW
0 MW1.0 GW2.0 GW2033: 1.0 GW2037: 1.3 GW2033203520371.3 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20331,030.2 MW
20371,254.2 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Knockton Wind Farm130.2 MW0 MW31 Oct 2033not statedgate not printedScoping
2ALYTH ENERGY STORAGE AND SOLAR400 MW130.2 MW31 Oct 20331gate 1Scoping
3Brigton of Ruthven BESS500 MW530.2 MW31 Oct 2033not statedgate not printedScoping
4Glenmoy Wind Solar & BESS224 MW1,030.2 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203331,030.2 MW
20371224 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Brigton of Ruthven BESSBattery storage500 MW31 Oct 2033Scoping
ALYTH ENERGY STORAGE AND SOLARHybrid400 MW31 Oct 2033Scoping
Glenmoy Wind Solar & BESSHybrid224 MW31 Oct 2037Scoping
Knockton Wind FarmOnshore wind130.2 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.