N84 Grid

Amersham Main 132kV Substation

NESO connection site, host NGET.

Contracted here0.38 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue375.18 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Amersham BESS & Substation31 May 202431 Oct 2034249.9 MW
Vox Charlie31 May 202431 Oct 2037125.28 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2034: 250 MW2037: 375 MW2034203520362037375 MW
0 MW200 MW400 MW2034: 250 MW2037: 375 MW2034203520362037375 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2034249.9 MW
2037375.18 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Amersham BESS & Substation249.9 MW0 MW31 Oct 2034not statedgate not printedScoping
2Vox Charlie125.28 MW249.9 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20341249.9 MW
20371125.28 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Amersham BESS & SubstationBattery storage249.9 MW31 Oct 2034Scoping
Vox CharlieBattery storage125.28 MW31 Oct 2037Scoping
Bumpers Farm BESS phase 2Battery storage49.5 MWnot statedBuilt
Bumpers Farm BESS phase 1Battery storage49.5 MWnot statedBuilt
AmershamBattery storage0 MWnot statedScoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.