The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Arbroath Battery Substation
31 May 2024 to 21 Feb 2022, date already passed (gate not printed) - Packhouse Solar
7 Nov 2025 to 28 Feb 2023, date already passed (gate not printed) - Parkhill South Solar Farm
7 Nov 2025 to 30 Sep 2024, date already passed (gate not printed) - BLINDWELLS FARM BESS
7 Nov 2025 to 30 Jun 2032 (gate not printed) - Craigend
20 Dec 2024 to 30 Jun 2032 (gate not printed) - Land at Sir William Smith Road
7 Nov 2025 to 31 Oct 2032 (gate 1) - Locharber
31 May 2024 to 31 Oct 2032 (gate not printed) - DENFIELD 20MW BESS
7 Nov 2025 to 31 Oct 2032 (gate not printed) - Balmachie Farm
7 Nov 2025 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Arbroath Battery Substation | 31 May 2024 | 21 Feb 2022 | 35 MW |
| Packhouse Solar | 7 Nov 2025 | 28 Feb 2023 | 0.18 MW |
| Parkhill South Solar Farm | 7 Nov 2025 | 30 Sep 2024 | 9.9 MW |
| BLINDWELLS FARM BESS | 7 Nov 2025 | 30 Jun 2032 | 50 MW |
| Craigend | 20 Dec 2024 | 30 Jun 2032 | 49.9 MW |
| Land at Sir William Smith Road | 7 Nov 2025 | 31 Oct 2032 | 49.9 MW |
| Locharber | 31 May 2024 | 31 Oct 2032 | 50 MW |
| DENFIELD 20MW BESS | 7 Nov 2025 | 31 Oct 2032 | 20 MW |
| Balmachie Farm | 7 Nov 2025 | 31 Oct 2033 | 30 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2022 | 35 MW |
| 2023 | 35.18 MW |
| 2024 | 45.08 MW |
| 2032 | 264.88 MW |
| 2033 | 294.88 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Arbroath Battery Substation | 35 MW | 0 MW | 21 Feb 2022 | not stated | gate not printed | Consents Approved |
| 2 | Packhouse Solar | 0.18 MW | 35 MW | 28 Feb 2023 | not stated | gate not printed | Scoping |
| 3 | Parkhill South Solar Farm | 9.9 MW | 35.18 MW | 30 Sep 2024 | not stated | gate not printed | Scoping |
| 4 | BLINDWELLS FARM BESS | 50 MW | 45.08 MW | 30 Jun 2032 | not stated | gate not printed | Awaiting Consents |
| 5 | Craigend | 49.9 MW | 95.08 MW | 30 Jun 2032 | not stated | gate not printed | Scoping |
| 6 | Land at Sir William Smith Road | 49.9 MW | 144.98 MW | 31 Oct 2032 | 1 | gate 1 | Scoping |
| 7 | Locharber | 50 MW | 194.88 MW | 31 Oct 2032 | not stated | gate not printed | Scoping |
| 8 | DENFIELD 20MW BESS | 20 MW | 244.88 MW | 31 Oct 2032 | not stated | gate not printed | Scoping |
| 9 | Balmachie Farm | 30 MW | 264.88 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2022 | 1 | 35 MW |
| 2023 | 1 | 0.18 MW |
| 2024 | 1 | 9.9 MW |
| 2032 | 5 | 219.8 MW |
| 2033 | 1 | 30 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Locharber | Hybrid | 50 MW | 31 Oct 2032 | Scoping |
| BLINDWELLS FARM BESS | Battery storage | 50 MW | 30 Jun 2032 | Awaiting Consents |
| Craigend | Solar | 49.9 MW | 30 Jun 2032 | Scoping |
| Land at Sir William Smith Road | Battery storage | 49.9 MW | 31 Oct 2032 | Scoping |
| Arbroath Battery Substation | Battery storage | 35 MW | 21 Feb 2022 | Consents Approved |
| Balmachie Farm | Hybrid | 30 MW | 31 Oct 2033 | Scoping |
| DENFIELD 20MW BESS | Battery storage | 20 MW | 31 Oct 2032 | Scoping |
| Parkhill South Solar Farm | Solar | 9.9 MW | 30 Sep 2024 | Scoping |
| New Mains of Guynd PV | Solar | 9.5 MW | not stated | Built |
| New Mains of Kinblethmont PV | Solar | 5 MW | not stated | Built |
| Parkhill Farm PV | Solar | 4.99 MW | not stated | Built |
| Packhouse Solar | Solar | 0.18 MW | 28 Feb 2023 | Scoping |