N84 Grid

Arecleoch 132/33kV

NESO connection site, host SPT.

Contracted here0.29 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Aug 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue288.8 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Arecleoch Extension Windfarm31 May 202431 Aug 202672.8 MW
Arecleoch31 May 202415 Jun 2032216 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 73 MW2032: 289 MW2026202720282029203020312032289 MW
0 MW200 MW400 MW2026: 73 MW2032: 289 MW2026202820302032289 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202672.8 MW
2032288.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Arecleoch Extension Windfarm72.8 MW0 MW31 Aug 2026not statedgate not printedScoping
2Arecleoch216 MW72.8 MW15 Jun 2032not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026172.8 MW
20321216 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Arecleoch (SCOTTISHPOWER RENEWABLES (UK) LIMITED)Onshore wind330 MW15 Jun 2032Scoping
Arecleoch Extension WindfarmOnshore wind72.8 MW31 Aug 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.