Armadale 400kv Substation

NESO connection site, host SHET, SPT.

Contracted here0.36 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue360 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Galileo 1031 May 2024 to 31 Oct 2031 (gate not printed)
  • Elmya Bathgate BESS20 Dec 2024 to 31 Oct 2031 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Galileo 1031 May 202431 Oct 203160 MW
Elmya Bathgate BESS20 Dec 202431 Oct 2031300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2031: 360 MW2031360 MW
0 MW200 MW400 MW2031: 360 MW2031360 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031360 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Galileo 1060 MW0 MW31 Oct 2031not statedgate not printedScoping
2Elmya Bathgate BESS300 MW60 MW31 Oct 20311gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20312360 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Elmya Bathgate BESSBattery storage300 MW31 Oct 2031Scoping
Galileo 10Battery storage60 MW31 Oct 2031Scoping
Armadale Wind FarmHybrid0 MWnot statedAwaiting Consents

Supported by National Energy SO Open Data