Arresgill 132kV Substation

NESO connection site, host SPT.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue199 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Arresgill Wind Farm31 May 202431 Oct 2031150 MW
Arresgill Energy Storage 131 May 202431 Oct 203149 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2031: 199 MW2031199 MW
0 MW100 MW200 MW2031: 199 MW2031199 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031199 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Arresgill Wind Farm150 MW0 MW31 Oct 20311gate 1Scoping
2Arresgill Energy Storage 149 MW150 MW31 Oct 20311gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20312199 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Arresgill Wind FarmOnshore wind150 MW31 Oct 2031Scoping
Arresgill Energy Storage 1Battery storage49 MW31 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.