Axminster 132kV Substation

NESO connection site, host NGET.

Contracted here0.64 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Oct 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue639.9 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Axminster31 May 202431 Oct 2024120 MW
Axminster31 May 202431 Oct 202749.9 MW
Axminster BESS31 May 202431 Oct 2028150 MW
Axminster - New Connection31 May 202430 Jun 2029120 MW
Old Park Farm31 May 202431 Oct 2038200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2024: 120 MW2027: 170 MW2028: 320 MW2029: 440 MW2038: 640 MW20242026202820302032203420362038640 MW
0 MW400 MW800 MW2024: 120 MW2027: 170 MW2028: 320 MW2029: 440 MW2038: 640 MW2024202820322038640 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2024120 MW
2027169.9 MW
2028319.9 MW
2029439.9 MW
2038639.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Axminster120 MW0 MW31 Oct 20241gate 1Awaiting Consents
2Axminster49.9 MW120 MW31 Oct 20271gate 1Scoping
3Axminster BESS150 MW169.9 MW31 Oct 20281gate 1Scoping
4Axminster - New Connection120 MW319.9 MW30 Jun 20291gate 1Scoping
5Old Park Farm200 MW439.9 MW31 Oct 2038not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20241120 MW
2027149.9 MW
20281150 MW
20291120 MW
20381200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Old Park FarmHybrid200 MW31 Oct 2038Scoping
Axminster BESSBattery storage150 MW31 Oct 2028Scoping
Axminster - New ConnectionBattery storage120 MW30 Jun 2029Scoping
Axminster (HB825AXM LTD)Battery storage120 MW31 Oct 2024Awaiting Consents
Axminster (PIVOTED POWER LLP)Battery storage49.9 MW31 Oct 2027Scoping