The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Axminster
31 May 2024 to 31 Oct 2024, date already passed (gate 1) - Axminster
31 May 2024 to 31 Oct 2027 (gate 1) - Axminster BESS
31 May 2024 to 31 Oct 2028 (gate 1) - Axminster - New Connection
31 May 2024 to 30 Jun 2029 (gate 1) - Old Park Farm
31 May 2024 to 31 Oct 2038 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Axminster | 31 May 2024 | 31 Oct 2024 | 120 MW |
| Axminster | 31 May 2024 | 31 Oct 2027 | 49.9 MW |
| Axminster BESS | 31 May 2024 | 31 Oct 2028 | 150 MW |
| Axminster - New Connection | 31 May 2024 | 30 Jun 2029 | 120 MW |
| Old Park Farm | 31 May 2024 | 31 Oct 2038 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 120 MW |
| 2027 | 169.9 MW |
| 2028 | 319.9 MW |
| 2029 | 439.9 MW |
| 2038 | 639.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Axminster | 120 MW | 0 MW | 31 Oct 2024 | 1 | gate 1 | Awaiting Consents |
| 2 | Axminster | 49.9 MW | 120 MW | 31 Oct 2027 | 1 | gate 1 | Scoping |
| 3 | Axminster BESS | 150 MW | 169.9 MW | 31 Oct 2028 | 1 | gate 1 | Scoping |
| 4 | Axminster - New Connection | 120 MW | 319.9 MW | 30 Jun 2029 | 1 | gate 1 | Scoping |
| 5 | Old Park Farm | 200 MW | 439.9 MW | 31 Oct 2038 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 120 MW |
| 2027 | 1 | 49.9 MW |
| 2028 | 1 | 150 MW |
| 2029 | 1 | 120 MW |
| 2038 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Old Park Farm | Hybrid | 200 MW | 31 Oct 2038 | Scoping |
| Axminster BESS | Battery storage | 150 MW | 31 Oct 2028 | Scoping |
| Axminster - New Connection | Battery storage | 120 MW | 30 Jun 2029 | Scoping |
| Axminster (HB825AXM LTD) | Battery storage | 120 MW | 31 Oct 2024 | Awaiting Consents |
| Axminster (PIVOTED POWER LLP) | Battery storage | 49.9 MW | 31 Oct 2027 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.