The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Easter Drumclair Generator
7 Nov 2025 to 30 Nov 2022, date already passed (gate not printed) - Torrance Farm Extension 2
7 Nov 2025 to 30 Sep 2025, date already passed (gate not printed) - Southrigg 2 Wind Farm
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Heights Wind Farm
7 Nov 2025 to 30 Sep 2026, date already passed (gate not printed) - Tormywheel Extension WF
7 Nov 2025 to 29 Oct 2026 (gate not printed) - Forrestfield Wind Farm
7 Nov 2025 to 29 Nov 2026 (gate not printed) - Woolfords Wind Farm
7 Nov 2025 to 29 Aug 2031 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Easter Drumclair Generator | 7 Nov 2025 | 30 Nov 2022 | 6 MW |
| Torrance Farm Extension 2 | 7 Nov 2025 | 30 Sep 2025 | 21.6 MW |
| Southrigg 2 Wind Farm | 7 Nov 2025 | 31 Oct 2025 | 8.4 MW |
| Heights Wind Farm | 7 Nov 2025 | 30 Sep 2026 | 9.8 MW |
| Tormywheel Extension WF | 7 Nov 2025 | 29 Oct 2026 | 9.4 MW |
| Forrestfield Wind Farm | 7 Nov 2025 | 29 Nov 2026 | 9 MW |
| Woolfords Wind Farm | 7 Nov 2025 | 29 Aug 2031 | 19.8 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2022 | 6 MW |
| 2025 | 36 MW |
| 2026 | 64.2 MW |
| 2031 | 84 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Easter Drumclair Generator | 6 MW | 0 MW | 30 Nov 2022 | not stated | gate not printed | Awaiting Consents |
| 2 | Torrance Farm Extension 2 | 21.6 MW | 6 MW | 30 Sep 2025 | not stated | gate not printed | Scoping |
| 3 | Southrigg 2 Wind Farm | 8.4 MW | 27.6 MW | 31 Oct 2025 | not stated | gate not printed | Scoping |
| 4 | Heights Wind Farm | 9.8 MW | 36 MW | 30 Sep 2026 | not stated | gate not printed | Scoping |
| 5 | Tormywheel Extension WF | 9.4 MW | 45.8 MW | 29 Oct 2026 | not stated | gate not printed | Scoping |
| 6 | Forrestfield Wind Farm | 9 MW | 55.2 MW | 29 Nov 2026 | not stated | gate not printed | Awaiting Consents |
| 7 | Woolfords Wind Farm | 19.8 MW | 64.2 MW | 29 Aug 2031 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2022 | 1 | 6 MW |
| 2025 | 2 | 30 MW |
| 2026 | 3 | 28.2 MW |
| 2031 | 1 | 19.8 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Tormywheel | Onshore wind | 37.45 MW | not stated | Built |
| Burnhead Wind Farm | Onshore wind | 29.5 MW | not stated | Built |
| Torrance Farm Extension 2 | Onshore wind | 21.6 MW | 30 Sep 2025 | Scoping |
| Woolfords Wind Farm | Onshore wind | 19.8 MW | 29 Aug 2031 | Scoping |
| Heights Wind Farm | Onshore wind | 9.8 MW | 30 Sep 2026 | Scoping |
| Tormywheel Extension WF | Onshore wind | 9.4 MW | 29 Oct 2026 | Scoping |
| Forrestfield Wind Farm | Onshore wind | 9 MW | 29 Nov 2026 | Awaiting Consents |
| Torrance Warm Wind Farm | Onshore wind | 9 MW | not stated | Built |
| Southrigg 2 Wind Farm | Onshore wind | 8.4 MW | 31 Oct 2025 | Scoping |
| Easter Drumclair Generator | Onshore wind | 6 MW | 30 Nov 2022 | Awaiting Consents |
| Drumduff Wind Farm | Onshore wind | 6 MW | not stated | Built |
| Torrance Wind Farm Extension | Onshore wind | 6 MW | not stated | Built |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.