Bishops Wood 132kV Substation

NESO connection site, host NGET.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Jun 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue219.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lincomb Farm 120MW BESS Scheme31 May 202430 Jun 2033120 MW
Valley Farm22 Jul 202531 Oct 203799.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2033: 120 MW2037: 220 MW20332034203520362037220 MW
0 MW125 MW250 MW2033: 120 MW2037: 220 MW203320352037220 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033120 MW
2037219.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lincomb Farm 120MW BESS Scheme120 MW0 MW30 Jun 20331gate 1Scoping
2Valley Farm99.9 MW120 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20331120 MW
2037199.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Lincomb Farm 120MW BESS SchemeBattery storage120 MW30 Jun 2033Scoping
Valley FarmBattery storage99.9 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.