The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Berwick Bank Offshore Wind Farm C
31 May 2024 to 30 Nov 2029 (gate not printed) - Icewind Blyth
31 May 2024 to 31 Oct 2031 (gate 1) - Hope Battery Storage
31 May 2024 to 31 Oct 2036 (gate 1) - Blyth BESS
31 May 2024 to 31 Oct 2036 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Berwick Bank Offshore Wind Farm C | 31 May 2024 | 30 Nov 2029 | 1,800 MW |
| Icewind Blyth | 31 May 2024 | 31 Oct 2031 | 1,000 MW |
| Hope Battery Storage | 31 May 2024 | 31 Oct 2036 | 400 MW |
| Blyth BESS | 31 May 2024 | 31 Oct 2036 | 450 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 1,800 MW |
| 2031 | 2,800 MW |
| 2036 | 3,650 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Berwick Bank Offshore Wind Farm C | 1,800 MW | 0 MW | 30 Nov 2029 | not stated | gate not printed | Scoping |
| 2 | Icewind Blyth | 1,000 MW | 1,800 MW | 31 Oct 2031 | 1 | gate 1 | Scoping |
| 3 | Hope Battery Storage | 400 MW | 2,800 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
| 4 | Blyth BESS | 450 MW | 3,200 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 1,800 MW |
| 2031 | 1 | 1,000 MW |
| 2036 | 2 | 850 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm C | Offshore wind | 1,800 MW | 30 Nov 2029 | Scoping |
| NS Link | Interconnector | 1,400 MW | not stated | Built |
| Icewind Blyth | Offshore wind | 1,000 MW | 31 Oct 2031 | Scoping |
| Blyth BESS | Battery storage | 450 MW | 31 Oct 2036 | Scoping |
| Hope Battery Storage | Battery storage | 400 MW | 31 Oct 2036 | Scoping |
| Lynemouth Power Station | Biomass and waste | 396 MW | not stated | Built |
Supported by National Energy SO Open Data