N84 Grid

Boat of Garten GSP

NESO connection site, host SHET.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Dec 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue85 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Boat of Garten GSP7 Nov 202531 Dec 20230.1 MW
Boat of Garten BESS7 Nov 202530 Sep 202449.9 MW
Nan Clach Extension7 Nov 202531 Aug 203035 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2023: 0 MW2024: 50 MW2030: 85 MW2023202420252026202720282029203085 MW
0 MW50 MW100 MW2023: 0 MW2024: 50 MW2030: 85 MW202320252027203085 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20230.1 MW
202450 MW
203085 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Boat of Garten GSP0.1 MW0 MW31 Dec 2023not statedgate not printedScoping
2Boat of Garten BESS49.9 MW0.1 MW30 Sep 2024not statedgate not printedConsents Approved
3Nan Clach Extension35 MW50 MW31 Aug 2030not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202310.1 MW
2024149.9 MW
2030135 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Boat of Garten BESSBattery storage49.9 MW30 Sep 2024Consents Approved
Tom Nan ClachOnshore wind41 MWnot statedBuilt
Nan Clach ExtensionHybrid35 MW31 Aug 2030Scoping
Ardverikie and Corrour Estate HydroHydro and pumped storage8.6 MWnot statedBuilt
Boat of Garten GSP (Scottish Hydro Electric Power Distribution Plc)Solar0.1 MW31 Dec 2023Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.