N84 Grid

Braehead Park 132/33kV

NESO connection site, host SPT.

Contracted here0.15 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue149.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
South Clyde Energy Centre7 Nov 202530 Jun 202645 MW
Wright Street BESS31 May 202431 Oct 202549.9 MW
Glasgow Airport7 Nov 202530 Oct 20265 MW
Scottish Water Laigh Park STW22 Jul 202528 Jun 202850 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2025: 50 MW2026: 100 MW2028: 150 MW2025202620272028150 MW
0 MW100 MW200 MW2025: 50 MW2026: 100 MW2028: 150 MW2025202620272028150 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202549.9 MW
202699.9 MW
2028149.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1South Clyde Energy Centre45 MW0 MW30 Jun 20262gate 2Consents Approved
2Wright Street BESS49.9 MW45 MW31 Oct 2025not statedgate not printedScoping
3Glasgow Airport5 MW94.9 MW30 Oct 2026not statedgate not printedScoping
4Scottish Water Laigh Park STW50 MW99.9 MW28 Jun 20281gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025149.9 MW
2026250 MW
2028150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Scottish Water Laigh Park STWBattery storage50 MW28 Jun 2028Scoping
Wright Street BESSBattery storage49.9 MW31 Oct 2025Scoping
South Clyde Energy CentreBiomass and waste45 MW30 Jun 2026Consents Approved
Glasgow AirportSolar5 MW30 Oct 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.