N84 Grid

Bridge of Dun GSP

NESO connection site, host SHET.

Contracted here0.17 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue165.15 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
South Esk Solar Farm7 Nov 202531 Oct 20269.9 MW
Balwyllo BESS7 Nov 202530 Jun 203249.9 MW
Dunmill Energy Storage31 May 202430 Jun 203249.9 MW
Land at Kinnell Solar Farm7 Nov 202530 Jun 20329.45 MW
Mains of Dun Solar7 Nov 202530 Jun 203228 MW
Ballochy Solar Farm GSK7 Nov 202530 Jun 203218 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 10 MW2032: 165 MW2026202720282029203020312032165 MW
0 MW100 MW200 MW2026: 10 MW2032: 165 MW2026202820302032165 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20269.9 MW
2032165.15 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1South Esk Solar Farm9.9 MW0 MW31 Oct 2026not statedgate not printedScoping
2Balwyllo BESS49.9 MW9.9 MW30 Jun 20321gate 1Scoping
3Dunmill Energy Storage49.9 MW59.8 MW30 Jun 2032not statedgate not printedScoping
4Land at Kinnell Solar Farm9.45 MW109.7 MW30 Jun 2032not statedgate not printedScoping
5Mains of Dun Solar28 MW119.15 MW30 Jun 2032not statedgate not printedScoping
6Ballochy Solar Farm GSK18 MW147.15 MW30 Jun 2032not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202619.9 MW
20325155.25 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Balwyllo BESSBattery storage49.9 MW30 Jun 2032Scoping
Dunmill Energy StorageBattery storage49.9 MW30 Jun 2032Scoping
Mains of Dun SolarSolar28 MW30 Jun 2032Scoping
Ballochy Solar Farm GSKSolar18 MW30 Jun 2032Scoping
Tullo Wind FarmOnshore wind17 MWnot statedBuilt
South Esk Solar FarmSolar9.9 MW31 Oct 2026Scoping
Land at Kinnell Solar FarmHybrid9.45 MW30 Jun 2032Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.