N84 Grid

Brinsworth 400kV Substation

NESO connection site, host NGET.

Contracted here1.50 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,500 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Old Flatts Farm31 May 2024 to 30 Oct 2029 (gate not printed)
  • Old Flatts Farm31 May 2024 to 30 Oct 2035 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Old Flatts Farm31 May 202430 Oct 2029750 MW
Old Flatts Farm31 May 202430 Oct 2035750 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2029: 750 MW2035: 1.5 GW20292030203120322033203420351.5 GW
0 MW1.0 GW2.0 GW2029: 750 MW2035: 1.5 GW20292031203320351.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029750 MW
20351,500 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Old Flatts Farm750 MW0 MW30 Oct 2029not statedgate not printedScoping
2Old Flatts Farm750 MW750 MW30 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291750 MW
20351750 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Old Flatts FarmHybrid1,500 MW30 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.