N84 Grid

Broadford GSP

NESO connection site, host SHET.

Contracted here0.30 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date16 Apr 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue301.99 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Allt Na Moine Generating Station7 Nov 202516 Apr 20281.99 MW
Sleat Hybrid31 May 202431 Oct 2034100 MW
Broadford BESS20 Dec 202431 Oct 2034200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2028: 2 MW2034: 302 MW2028202920302031203220332034302 MW
0 MW200 MW400 MW2028: 2 MW2034: 302 MW2028203020322034302 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20281.99 MW
2034301.99 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Allt Na Moine Generating Station1.99 MW0 MW16 Apr 2028not statedgate not printedConsents Approved
2Sleat Hybrid100 MW1.99 MW31 Oct 20341gate 1Scoping
3Broadford BESS200 MW101.99 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202811.99 MW
20342300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Broadford BESSBattery storage200 MW31 Oct 2034Scoping
Sleat HybridHybrid100 MW31 Oct 2034Scoping
Allt Na Moine Generating StationHydro and pumped storage1.99 MW16 Apr 2028Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.