BRORA 132/33KV GRID SUPPLY POINT SUBSTATION

NESO connection site, host SHET.

Contracted here0.16 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date8 Mar 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue160.06 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Golspie Business Park7 Nov 20258 Mar 20240.06 MW
180/181 Clynelish Muir BESS7 Nov 202531 Oct 203050 MW
AULTCRAGGIE BESS20 Dec 202431 Oct 203450 MW
Crakaig Wind Energy Hub21 Mar 202531 Oct 203460 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2024: 0 MW2030: 50 MW2034: 160 MW202420262028203020322034160 MW
0 MW100 MW200 MW2024: 0 MW2030: 50 MW2034: 160 MW2024202720302034160 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20240.06 MW
203050.06 MW
2034160.06 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Golspie Business Park0.06 MW0 MW8 Mar 2024not statedgate not printedScoping
2180/181 Clynelish Muir BESS50 MW0.06 MW31 Oct 20301gate 1Scoping
3AULTCRAGGIE BESS50 MW50.06 MW31 Oct 20341gate 1Scoping
4Crakaig Wind Energy Hub60 MW100.06 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202410.06 MW
2030150 MW
20342110 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Crakaig Wind Energy HubHybrid60 MW31 Oct 2034Scoping
180/181 Clynelish Muir BESSBattery storage50 MW31 Oct 2030Scoping
AULTCRAGGIE BESSBattery storage50 MW31 Oct 2034Scoping
Golspie Business ParkHybrid0.06 MW8 Mar 2024Scoping

Supported by National Energy SO Open Data