N84 Grid

Burghmuir GSP

NESO connection site, host SHET.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Dec 2022Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue224.45 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Burghmuir Battery7 Nov 202531 Dec 202249.9 MW
Burghmuir GSP (DNO) Broxden Hub7 Nov 202531 May 20240.15 MW
Newhouse Energy Storage7 Nov 202531 Oct 202849.9 MW
Kinnon Park PV and Battery7 Nov 202531 Oct 202849.5 MW
Dupplin Solar7 Nov 202531 Oct 203575 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2022: 50 MW2024: 50 MW2028: 149 MW2035: 224 MW2022202420262028203020322035224 MW
0 MW125 MW250 MW2022: 50 MW2024: 50 MW2028: 149 MW2035: 224 MW2022202620302035224 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202249.9 MW
202450.05 MW
2028149.45 MW
2035224.45 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Burghmuir Battery49.9 MW0 MW31 Dec 2022not statedgate not printedConsents Approved
2Burghmuir GSP (DNO) Broxden Hub0.15 MW49.9 MW31 May 2024not statedgate not printedScoping
3Newhouse Energy Storage49.9 MW50.05 MW31 Oct 2028not statedgate not printedScoping
4Kinnon Park PV and Battery49.5 MW99.95 MW31 Oct 2028not statedgate not printedScoping
5Dupplin Solar75 MW149.45 MW31 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2022149.9 MW
202410.15 MW
2028299.4 MW
2035175 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Dupplin SolarHybrid75 MW31 Oct 2035Scoping
Burghmuir BatteryBattery storage49.9 MW31 Dec 2022Consents Approved
Newhouse Energy StorageBattery storage49.9 MW31 Oct 2028Scoping
Kinnon Park PV and BatteryHybrid49.5 MW31 Oct 2028Scoping
Aviva Project ProgressionBattery storage1.37 MWnot statedBuilt
Burghmuir GSP (DNO) Broxden HubHybrid0.15 MW31 May 2024Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.