Burwell South 400kV Substation

NESO connection site, host NGET.

Contracted here0.51 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue506.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rat Hall Solar31 May 202431 Oct 2032200 MW
ER BUR Energy31 May 202428 Oct 203357 MW
Burwell BESS31 May 202430 Oct 2034249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2032: 200 MW2033: 257 MW2034: 507 MW203220332034507 MW
0 MW400 MW800 MW2032: 200 MW2033: 257 MW2034: 507 MW203220332034507 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2032200 MW
2033257 MW
2034506.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rat Hall Solar200 MW0 MW31 Oct 20321gate 1Scoping
2ER BUR Energy57 MW200 MW28 Oct 20331gate 1Scoping
3Burwell BESS249.9 MW257 MW30 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20321200 MW
2033157 MW
20341249.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Burwell BESSHybrid249.9 MW30 Oct 2034Scoping
Rat Hall SolarHybrid200 MW31 Oct 2032Scoping
ER BUR EnergyHybrid57 MW28 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.