Butlers Wood 400kV Substation

NESO connection site, host NGET.

Contracted here1.36 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,355 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Butlers Wood Green Energy Centre31 May 202430 Oct 20311,025 MW
Zenobe Butler's Wood BESS31 May 202431 Oct 2034330 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2031: 1.0 GW2034: 1.4 GW20312032203320341.4 GW
0 MW1.0 GW2.0 GW2031: 1.0 GW2034: 1.4 GW20312032203320341.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20311,025 MW
20341,355 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Butlers Wood Green Energy Centre1,025 MW0 MW30 Oct 2031not statedgate not printedAwaiting Consents
2Zenobe Butler's Wood BESS330 MW1,025 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203111,025 MW
20341330 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Butlers Wood Green Energy CentreHybrid1,025 MW30 Oct 2031Awaiting Consents
Zenobe Butler's Wood BESSBattery storage330 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.