N84 Grid

Cellarhead 400kV Substation

NESO connection site, host NGET.

Contracted here1.68 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date13 Sep 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,680 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cellarhead 400kV Energy Storage31 May 202413 Sep 2028300 MW
Cellarhead Green Energy Centre31 May 202430 Oct 2028400 MW
Cellarhead Home Farm31 May 202431 Oct 2028280 MW
Cellarhead31 May 202431 Oct 2033400 MW
Thorney Edge31 May 202430 Nov 2037300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2028: 980 MW2033: 1.4 GW2037: 1.7 GW2028203020322034203620371.7 GW
0 MW1.0 GW2.0 GW2028: 980 MW2033: 1.4 GW2037: 1.7 GW20282031203420371.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028980 MW
20331,380 MW
20371,680 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cellarhead 400kV Energy Storage300 MW0 MW13 Sep 2028not statedgate not printedAwaiting Consents
2Cellarhead Green Energy Centre400 MW300 MW30 Oct 2028not statedgate not printedAwaiting Consents
3Cellarhead Home Farm280 MW700 MW31 Oct 2028not statedgate not printedScoping
4Cellarhead400 MW980 MW31 Oct 20331gate 1Scoping
5Thorney Edge300 MW1,380 MW30 Nov 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20283980 MW
20331400 MW
20371300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cellarhead (ENSO GREEN HOLDINGS X LIMITED)Hybrid400 MW31 Oct 2033Scoping
Cellarhead Green Energy CentreHybrid400 MW30 Oct 2028Awaiting Consents
Cellarhead 400kV Energy StorageBattery storage300 MW13 Sep 2028Awaiting Consents
Thorney EdgeBattery storage300 MW30 Nov 2037Scoping
Cellarhead Home FarmBattery storage280 MW31 Oct 2028Scoping
ChatterleyGas20 MWnot statedBuilt
Bird Grove/RownallSolar0 MW1 Jun 2024Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.